Brick & Cement Estimator Pakistan (2026)

Brick & Cement Estimator Pakistan

Enter your covered area and the calculator estimates the cement bags, steel, bricks, sand and crush your grey structure needs — with the cost at today’s rates. Free and easy.















Default rates are October 2026 Lahore dealer rates. Change any rate to match your local dealer. Quantities are rules of thumb per sq ft of covered area — add 5–10% for wastage.

For an RCC-frame house, plan about 0.4 bags of cement, 3.5 kg of steel, 22 bricks, 1.8 cft of sand and 1.35 cft of crush per sq ft of covered area. A 10 Marla house (3,375 sq ft) needs about 1,350 cement bags, 11,800 kg of steel and 74,250 bricks. Use the brick cement estimator Pakistan above to work out your own material list before you order.

brick cement estimator Pakistan — bright yellow modern house exterior
A modern house exterior.

How much material per sq ft?

These thumb rules come from Pakistani contractors and builders. For an RCC-frame house (columns, beams and slabs with 9-inch outer walls and 4.5-inch inner walls): cement 0.4 bag per sq ft, steel 3.5 kg, bricks 22, sand 1.8 cft, crush 1.35 cft. For a load-bearing brick house (walls carry the load, no frame): cement 0.24–0.31 bags, steel 1.4–1.9 kg, bricks 23–30, sand 1.2–2.5 cft, crush 0.57–0.87 cft per sq ft.

Material rates in Lahore (October 2026)

Cement (branded OPC, 50 kg bag): Rs 1,600–1,650. Steel Grade 60: Rs 248–270 per kg. A-class bricks: Rs 16–19 each. Chenab sand: Rs 95–120 per cft. Rates move every week with fuel prices and demand — check with your dealer on the day you buy. The Pakistan Bureau of Statistics averages for September 2026 were: cement Rs 1,586 a bag, steel Rs 231,380 a tonne, bricks Rs 24,831 per 1,000.

How to use the brick cement estimator Pakistan

Enter your covered area in square feet and pick your structure type. The calculator works out the cement bags, steel, bricks, sand and crush you need, and prices each one at the rate you set. Change any rate to match your local dealer. Add 5–10% extra for wastage when you order.

For the total build cost, see the Construction Cost calculator.

Use the brick cement estimator Pakistan again if your rates change.

FAQs

How many bricks are needed for a 5 Marla house?

About 44,000–53,000 bricks for an RCC-frame 5 Marla double-storey house (about 2,000 sq ft covered area at 22 bricks per sq ft). A load-bearing house needs more — about 46,000–60,000.

How many cement bags for a 10 Marla house?

About 1,350 bags for an RCC-frame 10 Marla house (3,375 sq ft at 0.4 bags per sq ft). Add 5–10% for wastage.

Does this include labour and finishing?

No. This estimator covers grey-structure material only — cement, steel, bricks, sand and crush. Labour, transport, plumbing, wiring, tiles, paint and fittings are separate.

Why do different guides give different numbers?

Because every house is different — wall thickness, number of columns, soil and design all change the quantities. These are rules of thumb for early budgeting. Your structural drawing and the builder’s bill of quantities give the exact numbers.

Sources

Thumb rules and rates on this page come from: Which.pk — Construction Material Calculator (https://which.pk/property/tools/construction-material-estimator/) (September 2026 PBS prices), Al Safat Builder — Construction Material Cost Calculator (https://alsafatbuilder.com.pk/construction-calculators/construction-material-cost-calculator/) (October 2026), Al Safat Builder — Construction Material Estimator (https://alsafatbuilder.com.pk/construction-calculators/construction-material-estimator/) (October 2026), Qaaf — House Construction Cost Calculator Pakistan 2026 (https://qaaf.com.pk/house-construction-cost-calculator/), and Marot Properties — Cement, Steel and Bricks Quantity (https://marotproperties.com/cement-steel-bricks-quantity-house-construction). All figures are planning ranges, checked on 27 November 2026.